Board of Supervisors Meeting
Minutes
7:30 p.m.,
September 8, 2008
Present: Stephen R. Conary,
Georgia F. Brutscher, Lauressa J. McNemar, P.E.
1. Call to order: The meeting was called to order at 7:30 p.m. by Conary.
2. Pledge of
Allegiance.
3. Announcements: Conary
announced upcoming meetings as follows: (a) September 11th at 1:00 p.m.,
with State
Representative Stephen Barrar to discuss the
Route 926 Bridge closure; (b) September 16th the Board will meet
representatives from Toll Brothers and the
4. Regester Associates — Berlin Lot #2, Corinne
Road: Jim Fritsch, P.E., Regester Associates on
behalf of Berlin Construction, joined by Jeff Berlin, Gerald McCormick,
Esquire, and Donna and Charles Maston, the purchasers
of Lot 2. Fritsch provided an update to the Discussion Plan to the Building
Permit Plan Lot
The Township Engineer Review Letter for Lot 1 Building Permit dated August 25, 2008 was reviewed as follows: (1) Township Engineer requests calculations using the adjusted design infiltration rate for the drywells. Fritsch will complete percolation tests on or before September 9, 2008; (2) Fritsch will provide Township Engineer with executed copies of the Operation and Maintenance Agreements and Plans for Lots 1 and 2; (3) Township Engineer requests the Plans be revised to show the extent of protected resources on the site. Fritsch requested direction on why a drainage area plan is required. McCormick requested clarification as to who will enforce provisions of the natural resource area. A general discussion ensued regarding current ordinances that prohibit tree harvesting and therefore limits further destruction of trees on the lots; (4) Fritsch agreed to discuss the revisions asked for to the Drainage Area Plan with the Township Engineer; (5) Fritsch reported that the walking trail is completed; and (6) Fritsch responded that the drywell in the steep slope area was shifted to avoid the trees. The Applicant can relocate the drywell per the Review Letter.
Finally, the Board agreed that the intent of the Township Natural
Resource Ordinance was to prevent clear cutting and to preserve woodland. The
Board agreed that Fritsch and the Applicant should speak to the Township
Engineer for clarification regarding the revisions requested in the August 25,
2008 Review Letter. Fritsch noted the Applicant’s frustration with the building
permit review process. The Secretary could not confirm if the Building
Inspector completed review of the permit application for
5. Public Comment:
a) Tom Pancoast requested the Secretary execute a letter of reduction for the White Farm subdivision reflecting escrow releases to date. He also recounted the difficulties he and many contractors have with the synthetic matting system recommended by the Township Engineer to protect grass seed. He would like the Board to make the Township Engineer aware that the mat is easily caught in mowers and it bakes and burns the seed that sprouts.
b) Zeke Hubbard expressed his appreciation for the use of
6. Project Manager Update: Sellers provided a written status report. Following is a brief synopsis of the report:
a)
b)
c) DCNR Trails Project — The Trails Feasibility Study Committee met on September 15, 2008 to approve the latest revised plan submitted by Regester Associates and the Brandywine Conservancy. A number of easements must be obtained in order to connect trails from the County property. A public meeting should be scheduled during the October 27, 2008.
d) County Trails Construction Project — Sellers reported that
discussion continues to resolve a stream-crossing problem east of Pocopson
Home. The Highway Occupancy Permit to cross Wawaset
should be approved along with the County trail easement for the County retained
parcel. The Township should review the total project funding by end of 2008,
prepare a payment request, and ask to extend the balance in funding into 2009.
He noted a November deadline for applications for open space and trail funding
for 2009. He recommended requesting a carryover of funding in order to complete
important links of major segments that need to move ahead. McNemar agreed to
research the need for individual easements as acquisition of the easements may
or may not necessitate the surveying of the entire wetlands. Harwood added that
work on the County trails has stopped due to soil conservation issues. The
County Conservation Office should be contacted regarding permitting
requirements. Secretary raised the question submitted by Don Thompson to plant
the tree screen along
e) Other trail issues — Sellers reported that nearly two (2) years have passed since approval was granted from PA Department of Environmental Protection for a bridge across the Pocopson Creek to serve the Overlook Subdivision.
7. Public Works: Brutscher
requested and Harwood agreed to Public Works Team assisting with Founders Day
(FD) set up on Friday from 10:00 a.m. to noon. She also asked
Harwood to secure the sagging FD advertising banners along the roadways.
McNemar volunteered to remove trash at the conclusion of Founders Day. Harwood
reported that work on the schoolhouse is complete although the rope bell is not
functioning and Public Works will do what they can to repair the cracked glass
in the window. Conary reminded everyone in attendance that FD issues should be
addressed in advance of the event rather than four days out. Harwood reported
that due to permitting issues the trail construction on the County transfer
property has stopped fifty feet (50') on either side of the stream. Harwood
updated the Board regarding a number of scheduled tasks citing chipping
available November 3 through November 6,
8. Old Business: Secretary
reported that revised agreements and legal descriptions will be submitted this
week for the vacating of
9. New Business:
a) Reschedule September 22, 2008 meeting — The Board agreed that the regular, fourth Monday of the month meeting on September 22nd must be cancelled due to scheduling conflicts. The Secretary will work with McNemar and Brutscher to reschedule and advertise the meeting.
b) Burnett Subdivision — Board discussed the Township Engineer Review Letter dated June 23, 2008, regarding waiver of a fracture trace analysis per Code Section 250-17.B(7). During their March 2008 meeting, the Planning Commission recommended the Board waive the requirement provided that the each of the deeds for Lots 1, 2, and 3 include an easement for installation of replacement septic, sewage facilities, and stormwater management infiltration systems. The Board will review final revisions to the Conservation Easement expected to be submitted this month with particular attention to be paid to manure management.
Motion: Brutscher moved to grant a waiver from the fracture trace analysis requirement per Code Section 250-17.B(7) provided that the deeds for lots 1, 2, and 3 include easements for the installation of replacement septic or sewage facilities and stormwater management infiltration systems to each of the owners of lots 1, 2, and 3; McNemar seconded; unanimously approved.
10. Escrow/Bond Releases: none at this time.
11. Treasurer’s Warrants: Warrant sheets approved as submitted.
12. Correspondence: Zeke
Hubbard, Chair, Park, Trails and Recreation Committee, presented a letter to
the Board requesting that the Board hire a part-time or contract employee to
act as implementation manager to oversee the park facilities at the direction
of the Committee. Hubbard also noted that administrative secretarial support is
no longer provided for the Committee. The Board acknowledged minimal
availability for administrative secretarial support generally due to budgetary
constraints. McNemar agreed to attend the next Park, Trails and Recreation
Committee meeting in order to get a first-hand assessment of their tasks at
hand. Conary reminded Hubbard that the Board would like the Committee to submit
a draft fee schedule recommendation for use of park facilities.
13. Review of Minutes: Meeting of August 25, 2008.
Motion: Brutscher moved to approve minutes as corrected; Conary seconded; motion approved unanimously.
14. Adjournment: At 10:50 p.m., Conary moved to adjourn the meeting; Brutscher seconded.
___________________________ _____________________________
Susan E. Simone,
Township Secretary Georgia
F. Brutscher, Vice Chair