Board of Supervisors Meeting
Minutes
7:30 p.m., September 18, 2008
Present: Georgia
Brutscher, Lauressa McNemar
1. Call to order: The meeting was called to order at 5:00 p.m. by Ms. Brutscher.
2. Treasurer’s Warrants
Three sets of
warrants were approved as submitted:
One of the bills
that was approved was VanDemark & Lynch’s invoice for MS-4 work performed
in 2008. McNemar commented that she was not in agreement with the level of
effort expended in 2008; however, the Township agreed to pay the invoice and,
moving forward, will have clearer communication about what tasks are to be
completed as part of the 2009 MS-4 Report.
The Parks,
Recreation & Trails warrant included the purchase of 6 wooden picnic tables
for the Pavilion at
3. Request to grant extension of conditional use
application for Kretzschmar property at
Motion: Brutscher moved to approve the request because work is occurring, just more slowly than the 6 month period originally
approved; seconded by McNemar; approved unanimously.
4. Toll/Riverside
McNemar reported
that based on a field visit of September 16, 2008, concerns about placement and
construction of the trail between Riverside and Pocopson Elementary School can
be adequately addressed within the $124,800 held back from Escrow Request #5 revised,
which was originally approved in December, 2008.
Motion: McNemar moved to release Escrow Release #5 Revised, which retains
$124,800 for future work on the aforementioned trail; Brutscher seconded;
approved unanimously.
Motion: McNemar
moved to authorize the Township Engineer to recommend remedies to the trail
situation mentioned above, provided that those services are clearly outlined
and paid for by Toll out of existing escrow funds; Brutscher seconded; approved
unanimously.
5. Other Business
A draft response to the
Burnetts’ letter questioning bills from the Township Engineer was reviewed by the
BOS and revised by Brutscher. It will be mailed with the response letter prepared
by the Township Engineer to the Burnetts on September 19.
A draft letter to H.W.
Sellers, Consultant, detailing BOS conversations regarding his contract terms and
work assignments, was reviewed by the BOS and revised by Brutscher. A second
draft will be e-mailed to Brutscher and McNemar for review on September 19 so
that a final version can be mailed to Mr. Sellers by September 23.
There was discussion
of the Grace property on
Adjournment: The meeting was adjourned at 5:35 p.m.
___________________________ _____________________________
Peggy Lennon, Acting
Secretary Georgia
F. Brutscher, Vice Chair